First Operating Segment – Skyline (East Kapolei to Aloha Stadium):

  • Opened service to the public on June 30, 2023.
  • Day-to-day operations and maintenance falls under the purview of the City Department of Transportation Services (DTS).

Second Operating Segment – (Joint Base Pearl Harbor-Hickam to Middle Street Transit Center):

  • Four (4) stations located at Pearl Harbor, Airport, Lagoon Drive, and Middle Street.
  • The Core Systems equipment installation of traction power, communications, automated train control, and platform screen gates is ongoing.
  • The “Third rail” energization began on June 17, 2024.
  • The anticipated transfer to DTS is scheduled for late 2025 for the opening of service.

 

Third Operating Segment – (Kalihi to Civic Center):

  • Six (6) future rail stations located at Kalihi, Honolulu Community College-Kapālama, Iwilei, Chinatown, Downtown, and Civic Center.
  • City Center Utilities Relocation work started in 2022 and is ongoing. The work will clear the way for future construction of the columns, guideway and stations.
  • Downtown Utilities Relocation: Expected to be complete in the first quarter of 2025.
  • Dillingham Utilities Relocation: Expected to be complete in the first quarter of 2026.
  • City Center Guideway and Stations Project: Notice to Proceed was issued on October 7, 2024, to Tutor Perini Corporation for the City Center Guideway and Stations design and construction.
  • The start of construction is estimated in the second-half of 2025.


Construction of this segment will be completed in 2030 and transferred to the Department of Transportation Services in 2031.

COMMUNITY MEETINGS:
HART and its Dillingham and Downtown Utilities Relocation contractors hold quarterly meetings to update the public on progress and upcoming activities.