Construction Overview

The Honolulu Rail Transit Project, excluding park-and-ride facilities, is currently separated into three segments.

Operating Segments

Segment 1

West Side Stations and Guideway (WSSG) | East Kapolei to Aloha Stadium

  • The first nine stations, 10 miles of the guideway, are complete: Kaualakaʻi (East Kapolei) Station, Keoneʻae (UH-West Oahu) Station, Honouliuli (Hoʻopili) Station, Hōʻaeʻae (West Loch) Station, Pouhala (Waipahu Transit Center) Station, Hālaulani (Leeward Community College) Station, Waiawa (Pearl Highlands) Station, Kalauao (Pearlridge) Station and Hālawa (Aloha Stadium) Station.
  • On June 9, 2023 HART transferred 10.75 miles of guideway, 9 stations, the 43-acre Rail Operations Center, and 12 four-car trains to City’s Department of Transportation Services (DTS). The Honolulu rail system, officially named the Skyline, opened on June 30, 2023.


For information on rail fares, schedules, safety, and operational questions, visit the Department of Transportation Services website. Skyline Hotline: 808-848-5555

Segment 2

Airport Guideway and Stations (AGS) | Aloha Stadium to Middle Street Transit Center

  • 5.2 miles of the rail guideway construction and trackwork is complete.
  • Construction of the four stations in this segment is expected to be sustainably complete in the first quarter 2025.
  • The stations include Makalapa (Joint Base Pearl Harbor-Hickam) Station, Lelepaua (Daniel K. Inouye International Airport) Station, Āhua (Lagoon Drive) Station, and Kahauiki (Middle Street) Station.
  • Installation activities for the core systems—including power cables, communications systems, and signaling equipment have begun.
  • Third rail energization started in June 2024, with vehicle train testing now underway.
  • Important Safety Reminder: Although, the rail stations in this segment may appear complete, they are still active work zones. The “third rail,” which powers the trains, is now energized and carries 750 volts of electricity, posing a fatal risk if you come into contact with it.
  • Anticipated transfer of assets to DTS is planned for late 2025 for the opening of service.

Segment 3

City Center | Middle Street Transit Center to Civic Center

  • Six (6) future rail stations at Kalihi, Honolulu Community College-Kapālama, Iwilei, Chinatown, Downtown, and Civic Center.
  • The staions inclde Mokauea (Kalihi) Station, Niuhelewai (Honolulu Community College-Kapālama) Station, Kūwili (Iwilei) Station, Hōlau (Chinatown) Station, Kuloloia (Downtown) Station, Kaʻākaukukui (Civic Center) Station.
  • Construction of this segment will be completed in 2030 and transferred to the Department of Transportation Services in 2031.
  • City Center Utilities Relocation work started in 2022 and is ongoing. The work includes relocating storm drainage facilities, sewer facilities, water main, gas and fuel, electrical and communications infrastructure, along with roadway improvements. These relocations are necessary for the future construction of columns, elevated guideway, and stations.
  • Downtown Utilities Relocation: Expected to be completed in the first quarter of 2025.
  • Dillingham Utilities Relocation: Expected to be completed in the first quarter of 2026.
  • Guideway and Stations Construction: Notice to Proceed issued on October 7, 2024, to Tutor Perini Corporation for the City Center Guideway and Stations design and construction.

 

More information:
Mauka Shift Plan — In 2021, HART implemented the “Mauka Shift” plan, which moves a portion of the rail alignment to the mauka (mountain) side of Dillingham Boulevard. This shift is expected to reduce the number of utilities that need to be relocated, minimize construction impacts, and shorten the project timeline.

Contracts and Timelines

Downtown Utilities Relocation:
This project is underway from Ka’aahi Street to Cooke Street, along Nimitz Highway and Halekauwila Street, ending at the intersection of Coral Street and Halekauwila Street. The contract was awarded to Frank V. Coluccio Construction Company, Inc. (FVCCC).


Dillingham Utilities Relocation:

Work is ongoing in the Kalihi-Palama area, beginning on Kamehameha Highway between Middle Street and Laumaka Street to the corner of Dillingham Boulevard and Kaaahi Street. The contract was awarded to Nan, Inc., and a Notice to Proceed was issued in October 2022.


City Center Guideway and Stations (CCGS) Design-Build Contract:
Awarded to Tutor Perini Corporation in August 2024; and a Notice to Proceed was issued on October 7, 2024. Project design begins immediately, while the start of construction is estimated in the second half of 2025.

Join Business and Community Meetings to learn more about the utility relocation projects. Visit our webpage for the latest information.

HART 2022 Recovery Plan

Construction Simulation: Dillingham Boulevard

HART’s 2022 Recovery Plan proposed an amendment to the original Full Funding Grant Agreement (FFGA), a contract between the City and County of Honolulu and the Federal Transit Administration (FTA) executed in 2012. The initial FFGA provided $1.55 billion in federal funding and outlined the project scope, 20 miles and 21 stations from East Kapolei to Ala Moana. However, when the project encountered challenges, HART submitted a 2022 Recovery Plan to the FTA, which proposed to truncate the project scope from the original 20 miles and 21 stations to 18.9 miles and 19 stations from the East Kapolei Station to the Civic Center Station; the FTA accepted this plan in September 2022.

The 2022 Recovery Plan also proposed the deferral of the Pearl Highlands Parking Garage. The scope change required an amendment to the Full Funding Grant Agreement (FFGA), which was necessary to maintain the funding needed to complete the remainder of the project.

Throughout 2023, HART collaborated with the FTA on amending the FFGA document, requiring approvals from various entities such as the U.S. Department of Transportation, the U.S. Congress, Governor’s Office, HART Board, City Council Committee on Budget, and Full City Council. By February 2024, the FFGA was executed, enabling the release of $125 million of the remaining $744 million federal funds, marking a significant milestone — the first appropriation from the FFGA in almost ten years.

The “HART Dillingham Construction Sequencing” video rendering is a visual guide to the planned utility relocation, guideway, and station construction along the Dillingham Corridor. While the video is representational and not an exact depiction of the work, it provides a general overview of the expected construction sequencing through project completion in March 2031.

Construction Simulation: Dillingham Boulevard

The “HART Dillingham Construction Sequencing” video rendering is a visual guide to the planned utility relocation, guideway, and station construction along the Dillingham Corridor. While the video is representational and not an exact depiction of the work, it provides a general overview of the expected construction sequencing through project completion in March 2031.

Traffic Updates and Alerts

Weekly Traffic Updates

Keep in touch with our weekly traffic updates and road closures along the rail alignment.

Construction Notices

HART Weekly eBlast

Our weekly newsletter will keep you up-to-date about the project, news, construction, and information on upcoming events.

Sign up for our weekly eBlast

Historic & Cultural Preservation

HART’s practices recognize the unique cultural qualities of Hawaii, both regionally as well as at the neighborhood level.  Our proactive sustainability efforts will highlight and preserve our ‘aina for future generations.

HART and Sustainability

Transit-oriented development (TOD) promotes the use of transit, walking, cycling, and reduced dependence on the private automobile through high-density commercial and residential development near high quality transit nodes, such as rail stations.

Project Status

The Overall Construction and Design Project Progress is based on the Estimate at Completion for the 2022 Recovery Plan scope to Ka‘ākaukukui (Civic Center) Station and the March 2031 Operational Readiness date.

Segment 1 Rail Now Open

For information on rail fares, schedules, safety, and operational questions, visit the Department of Transportation Services website. Skyline Hotline: 808-848-5555

Skip to content