Trial running is the final testing phase before operational readiness.
Trial Running (First Operating Segment):
- The final testing phase was conducted from August 29, 2022, to February 2023, simulating 144 scenarios of normal and emergency rail operations.
- As part of the comprehensive testing, the Trial Running phase involved simulating various normal and emergency operating scenarios, including a System Demonstration phase.
- Simulated the system’s operation as if it were open to the public.
- Achieved a 30-day rolling average of 98.5% on April 2, 2023.
Rail System Completion:
- Construction was completed for the first operating segment.
- Safety certification was finalized for a smooth turnover to the Department of Transportation Services (DTS).
HART has successfully completed testing, meeting reliability standards in the first operating segment. Stay tuned for updates on subsequent segments.