Trial run is the final testing phase before a segment is approved for passenger service.
First Operating Segment:
Trial operations were completed in April 2023. The segment passed System Demonstration and safety certification, allowing transfer to the City’s Department of Transportation Services (DTS).
Second Operating Segment:
Trial Run is expected to begin in July 2025. The System Demonstration must achieve an average of 98.5% availability over a rolling 30-day period.
All riders must exit at Aloha Stadium during testing. Trains will not carry passengers in Segment 2 until all safety requirements are met.