Home > Construction
Construction Overview
The Honolulu Rail Transit Project, excluding park-and-ride facilities, is currently divided into three construction segments.
Operating Segments
Segment 1
West Side Stations and Guideway (WSSG) | East Kapolei to Aloha Stadium
- Includes the first nine stations and 10.75 miles of fully completed guideway:
Kaualakaʻi (East Kapolei), Keoneʻae (UH-West Oʻahu), Honouliuli (Hoʻopili), Hōʻaeʻae (West Loch), Pouhala (Waipahu Transit Center), Hālaulani (Leeward Community College), Waiawa (Pearl Highlands), Kalauao (Pearlridge), and Hālawa (Aloha Stadium). - On June 9, 2023, HART transferred 10.75 miles of guideway, nine stations, the 43-acre Rail Operations Center, and twelve four-car trains to the City and County of Honolulu’s Department of Transportation Services (DTS).
 - Skyline’s Segment 1 opened to the public on June 30, 2023.
 
Segment 2
Airport Guideway and Stations (AGS) | Aloha Stadium to Middle Street Transit Center
- Includes four stations and 5.2 miles of fully completed guideway:
Pearl Harbor (Makalapa), Daniel K. Inouye International Airport (Lelepaua), Lagoon Drive (Āhua), and Middle Street (Kahauiki). - On October 1, 2025, HART transferred 5.2 miles of guideway, four stations, and 7 four-car trains to DTS.
 - Skyline’s Segment 2 opened to the public on October 16, 2025.
 
For information on fares, schedules, safety, and operations, visit the City’s Department of Transportation Services or call the Skyline Hotline at 808-848-5555.
Segment 3
City Center | Middle Street Transit Center to Civic Center
- Includes 3 miles of elevated guideway and six stations at Kalihi, Honolulu Community College-Kapālama, Iwilei, Chinatown, Downtown, and Civic Center.
 - Drilling of the first column shaft along Nimitz Highway began on October 16, 2025
 - Column construction expected to begin late 2025.
 - Downtown utilities is nearly complete, clearing the way for column construction.
 - Dillingham utility relocation is expected to be completed late 2026.
 - Neighborhood Station Design Workshops are underway for preliminary station designs in this segment.
 
Construction of Segment 3 is anticipated to be completed in 2030, with transfer to DTS by 2031.
City Center Utilities Relocation involved moving critical infrastructure including storm drains, sewer lines, water mains, gas and fuel lines, electrical systems, and communications lines along with roadway improvements. These relocations are necessary to support the construction of columns, elevated guideway and stations.
Contracts and Timelines
Downtown Utilities Relocation: 
This project runs from Kaʻaahi Street to Cooke Street, along Nimitz Highway and Halekauwila Street, ending at Coral Street and Halekauwila Street.
- Contract awarded to Frank V. Coluccio Construction Company, Inc. (FVCCC).
 - Work began in June 2022; expected completion in 2025
 - Construction Notice Flyer
 
Dillingham Utilities Relocation: 
Work is ongoing in the Kalihi-Palama area, starting along Kamehameha Highway between Middle Street and Laumaka Street, and continuing to Dillingham Boulevard and Kaʻaahi Street.
- Contract awarded to Nan, Inc.
 - Notice to Proceed issued: October 2022.
 - Work began in December 2022; expected completion late 2026.
 - Construction Notice Flyer
 
City Center Guideway and Stations (CCGS) Design-Build Contract:
This contract includes the design and construction of 3 miles of elevated guideway, six stations, and supporting infrastructure between the Middle Street Transit Center and Cooke Street.
- Contract awarded to Tutor Perini Corporation in August 2024.
 - Notice to Proceed issued: October 7, 2024; expected completion in 2030.
 
Join HART’s Business and Community Meetings virtually to learn more about the City Center Utility Relocation and Guideway and Station construction projects. Attend Neighborhood Design Workshops to interact with project representatives, ask questions, and share feedback on the preliminary design Segment 3 stations.
HART 2022 Recovery Plan
Construction Simulation: Dillingham Boulevard
HART’s 2022 Recovery Plan proposed an amendment to the original Full Funding Grant Agreement (FFGA), a contract between the City and County of Honolulu and the Federal Transit Administration (FTA) executed in 2012. The initial FFGA provided $1.55 billion in federal funding and outlined the project scope, 20 miles and 21 stations from East Kapolei to Ala Moana. However, when the project encountered challenges, HART submitted a 2022 Recovery Plan to the FTA, which proposed to truncate the project scope from the original 20 miles and 21 stations to 18.9 miles and 19 stations from the East Kapolei Station to the Civic Center Station; the FTA accepted this plan in September 2022.
The 2022 Recovery Plan also proposed the deferral of the Pearl Highlands Parking Garage. The scope change required an amendment to the Full Funding Grant Agreement (FFGA), which was necessary to maintain the funding needed to complete the remainder of the project.
Throughout 2023, HART collaborated with the FTA on amending the FFGA document, requiring approvals from various entities such as the U.S. Department of Transportation, the U.S. Congress, Governor’s Office, HART Board, City Council Committee on Budget, and Full City Council. By February 2024, the FFGA was executed, enabling the release of $125 million of the remaining $744 million federal funds, marking a significant milestone — the first appropriation from the FFGA in almost ten years.
The “HART Dillingham Construction Sequencing” video rendering is a visual guide to the planned utility relocation, guideway, and station construction along the Dillingham Corridor. While the video is representational and not an exact depiction of the work, it provides a general overview of the expected construction sequencing through project completion in March 2031.
Construction Simulation: Dillingham Boulevard
The “HART Dillingham Construction Sequencing” video rendering is a visual guide to the planned utility relocation, guideway, and station construction along the Dillingham Corridor. While the video is representational and not an exact depiction of the work, it provides a general overview of the expected construction sequencing through project completion in March 2031.
Traffic Updates and Alerts
Weekly Traffic Updates
Keep in touch with our weekly traffic updates and road closures along the rail alignment.
- Segment 1 – NO CLOSURES
 - Segment 1 – Week of July 6, 2025
 - Segment 1 – Week of June 29, 2025
 - Segment 1 – Week of June 22, 2025
 - Segment 1 – Week of June 15, 2025
 - Segment 1 – Week of June 8, 2025
 - Segment 1 – Week of June 1, 2025
 - Segment 1 – Week of May 25, 2025
 - Segment 1 – Week of May 18, 2025
 - Segment 1 – Week of May 11, 2025
 
- Segment 2 – Week of November 2, 2025
 - Segment 2 – Week of October 26, 2025
 - Segment 2 – Week of October 19, 2025
 - Segment 2 – Week of October 12, 2025
 - Segment 2 – Week of October 5, 2025
 - Segment 2 – Week of September 28, 2025
 - Segment 2 – Week of September 21, 2025
 - Segment 2 – Week of September 14, 2025
 - Segment 2 – Week of September 7, 2025
 - Segment 2 – Week of August 31, 2025
 
- Segment 3 – Week of November 2, 2025
 - Segment 3 – Week of October 26, 2025
 - Segment 3 – Week of October 19, 2025
 - Segment 3 – Week of October 12, 2025
 - Segment 3 – Week of October 5, 2025
 - Segment 3 – Week of September 28, 2025
 - Segment 3 – Week of September 21, 2025
 - Segment 3 – Week of September 14, 2025
 - Segment 3 – Week of September 7, 2025
 - Segment 3 – Week of August 31, 2025
 
Construction & Road Closure Notices
HART Weekly eBlast
Our weekly newsletter will keep you up-to-date about the project, news, construction, and information on upcoming events.
Historic & Cultural Preservation
HART’s practices recognize the unique cultural qualities of Hawaii, both regionally as well as at the neighborhood level. Our proactive sustainability efforts will highlight and preserve our ‘aina for future generations.
HART and Sustainability
Transit-oriented development (TOD) promotes the use of transit, walking, cycling, and reduced dependence on the private automobile through high-density commercial and residential development near high quality transit nodes, such as rail stations.
Construction Update Video Gallery
Construction Updates
2:46
2:19
1:11
1:45
2:29
1:50
1:16
1:52
3:10
1:57
2:35
0:57
1:41
1:41
1:51
3:05
1:04
1:52
1:55
1:58
1:35
1:58
1:59
2:14
0:54
1:57
1:00
1:36
2:45
1:57
3:00
0:59
1:21
1:59
2:38
1:09
1:52
2:37
4:17
2:45
4:20
2:40
2:36
2:35
3:04
2:35
2:33
3:00
2:46
3:08
2:35
3:15
3:08
3:34
3:45
3:25
Project Status
The Overall Construction and Design Project Progress is based on the Estimate at Completion for the 2022 Recovery Plan scope to Ka‘ākaukukui (Civic Center) Station and the March 2031 Operational Readiness date.