First Operating Segment – Skyline (East Kapolei to Aloha Stadium):
- Opened service to the public on June 30, 2023.
- Day-to-day operations and maintenance falls under the purview of the City Department of Transportation Services (DTS).
Second Operating Segment – (Joint Base Pearl Harbor-Hickam to Middle Street Transit Center):
- Track and Guideway construction work is substantially complete.
- Construction of the 4 stations in this segment is expected to be substantially complete in the second quarter of 2024.
- HART has begun core systems installation of power cables, communications systems, and signaling equipment.
- Third rail energization is anticipated by mid-2024, followed by subsequent testing and commissioning.
- Anticipated transfer to DTS in 2025 for the opening of service.
Third Operating Segment – (Kalihi to Civic Center):
- City Center Utilities Relocation is ongoing. This relocation work will clear the way for future construction of the columns, guideway and stations.
- Downtown Utilities Relocation work is expected to be complete in the fourth quarter of 2024.
- Dillingham Utilities Relocation work is expected to be complete in the first quarter of 2026.
Community Meetings:
HART and its Dillingham and Downtown Utilities Relocation contractors hold quarterly meetings to update the public on progress and upcoming activities.