HART receives a $500K Brownfields Assessment Grant from EPA
The Honolulu Authority for Rapid Transportation (HART) was selected to receive a $500,000 Brownfields Assessment Grant.
City Center Utilities Relocation (CCUR) III Construction Contract
HART has awarded the City Center Utilities Relocation (CCUR) III construction contract to Frank V. Coluccio Construction Company, Inc (FVCCC). This phase of utility relocation work is anticipated to start in mid-June 2022. The intent of this project is to relocate both wet and dry utilities from Ka’a’ahi Street, Nimitz Highway and Halekauwila Street in advance of the City Center Guideway and Stations (CCGS) contract. Both daytime and nighttime work is anticipated with periods of 24/7 construction in select areas on an as-needed basis.